Build the rate from first principles
A civil rate is a crew, its plant, materials, subcontractors and disposal, over what they produce in a day. Change the production rate and the price should move.
In Stralos each rate is worked out from tasks, each with its crew, plant and materials and a production rate. Item 3.01 is 220 m of DN300 stormwater pipe at a production rate of 30 m a day: 7.33 days of work for a crew of five with a 13.5 t and a 5.5 t excavator and a shared tipper, 66 hours each for the crew and both excavators. With the truck, pipe, metal, cleanfill and cartage, it costs NZ$397.69 a metre and goes in the tender at NZ$439.96.