How does a production rate become days and a cost per unit?
The quantity divided by the production rate gives the days, the days give the hours, and the cost per unit follows. One example from the example job: 220 m of DN300 stormwater at a production rate of 30 m a day is 7.33 days, 66 hours each for a crew of five, a 13.5 t and a 5.5 t excavator. With the shared tipper, pipe, metal, cleanfill and cartage, the item costs NZ$397.69 a metre. Change the rate and the days, hours and cost per unit move with it.
- Save typical production rates on a library activity, such as one for rock and one for clay, and pick one when you add it.
- Charge a line per day, week or month, per repeat, per unit, or once.
- Same crew label: the tasks run one after another. Different labels: side by side.